Tracking pixel

Lyndale Avenue

Eastham, Lyndale

Lyndale Avenue

SPECIFICATIONS

£5 million

PROJECT VALUE

June 2022

COMPLETION

18 months

DURATION

SPECIFICATIONS

Project Value: £5 million

Completion: June 2022

Duration: 18 months

BACKGROUND

Taking over the completion of this project when Cruden Construction went into administration, HMS ensured the redevelopment of the former Lyndale School site and the continuation of this development. With works on site halting not long after the foundations were laid, this site required the team to effectively manage and complete works.

Handing over 28 homes – all available via Affordable Rent and Shared Ownership – HMS finished all works and its resilience and ability to mobilise quickly saw the iconic local site repurposed to meet the homeownership needs of Eastham’s community.

Details


Location: Eastham, Lyndale

Client: Torus

Duration: 18 months

Completion: June 2022

Project Value: £5 million

Partners: John McCall Architects and Savills

LOCATION

STAY CONNECTED

Our newsletter, direct to your inbox. We take privacy seriously - we promise not to share your details with any other third party.